...
ERTG Claims Service Banner
Image text: "Biogas Yield Record High at Nigg WwTW".

Biogas Yield at Record High for Wastewater Sludge Digestion at Nigg WwTW

We are pleased to report that the biogas yield per tonne of sludge is once again at a record high for Wastewater Sludge Digestion at Nigg WwTW. Find out how this has been achieved in the Press Release below:


Press Release:

New biogas production landmark for Scottish Water’s acclaimed sludge facility at Nigg

If we took a short trip forward in time to 2040, and then looked back at how some organisations in the water industry successfully achieved Carbon Net Zero, it’s likely you’ll see a large four-letter word: NIGG.

This Scottish Water treatment centre in Aberdeen is currently leading the way as a centre of excellence for biogas production (from sludge), with its dedicated team tirelessly focused on improving efficiencies.  This is a place that believes in ‘better’. It is also the first wastewater treatment plant in the United Kingdom to successfully co-digest.

The Nigg Wastewater Treatment Works, which was built in 2002, has made some significant steps forward since Scottish Water took over ownership and operation in December, 2018; working with Cambi to upgrade the existing THP (thermal hydrolysis process) and importantly, installing a new digester mixing system, from Landia.

Large Gains in Biogas Yield /tonne Dry Solids

From initially producing 250 cubic metres of gas per tonne of dry solids, biogas yield has increased; first to 350, and has now climbed to an impressive 400 – 420.

Image text: "Biogas Yield Record High at Nigg WwTW".

The 400-plus biogas yield is also being achieved without unlimited, costly power.  Typically, if standard propellers were in use, around 17 watts per cubic metre would be required, but with the Landia system running at what amounts to less than 12 hours in a 24-hour period, only 7 watts per cubic metre are needed for the anaerobic digester mixing.

These latest numbers for biogas yield (at a site that has a small footprint for its energy output), are very much the result of fine-tuning and regular dialogue, as Nigg’s Operation Team Lead, Ewan Dickie, explains:

Mixing system Nigg by Landia
Easy to service outside the digester, the Landia Chopper Pump forms part of the mixing system at Nigg.

“It is imperative that we understand the equipment and processes in front of us”,

he said.

“And two years on since the latest improvements began at Nigg, Landia is always there to answer any questions we have about enhancing the mixing of our digesters”.

Prior to the upgrade, the facility had switched off the old compressor mixing system that had all too regularly caused problematic pipe blockages.

The clean-out of the digesters for the upgrade revealed that 45% of the volume had been lost to grit and heavily compacted sludge. 

‘Extremely robust mixing system’ 

“Now,” added Ewan, “we have an extremely robust mixing system that comprehensively mixes our two 4000m3 digesters. We don’t get any problems. The mixers just sit in the background, working away. The equipment is also so much easier to maintain because it’s externally mounted”.

Further evidence of Nigg proving how much energy from sludge can be produced at a wastewater treatment facility is its use of the biogas and heat from the Combined Heat & Power units (CHPs) for the site’s new boiler. £0.5M pa is now being saved on fuel oil.

Combined Heat & Power Units

Two years ago, the original target set for utilizing the CHPs (supplied by Clarke Energy) was 56%.  It now stands at 73%. The CHPs were producing around 80% of the power required to run the site at Nigg. That figure has improved to the point where most of the time, Nigg is now exporting surplus energy to the National Grid.

In addition to the intake from a local population of around 300,000, Nigg imports sludge cake from a further six Scottish Water wastewater treatment centres, and has commercial waste delivered from approximately 30 tankers per day.
Nigg WwTW high biogas yielding digester-tank
Since introducing Landia’s digester mixing system and upgrading Cambi’s THP, CO2 emissions at Nigg have more than halved.

Since the introduction of the Landia digester mixing system and the upgrade of the Cambi THP, CO2 emissions have more than halved. The amount of biogas (biogas yield) being produced has risen by more than 30%.

In the first stage of the digester mixing process, the liquid (or sludge) is injected into the upper half of the tank, whilst biogas is aspirated from the top of the tank and mixed into the liquid.

This not only has the benefit of reducing buoyancy at the surface of the liquid but also sees the rising gas bubbles continue to mix after the pumps are switched off.

Cambi’s proven Thermal Hydrolysis Process (THP) exposes sewage sludge at Nigg to high temperatures (160oC to 180oC) and pressures (about 6 bar), typically for 20 to 30 minutes for each batch to ensure pathogen kill. Sterilized and hydrolyzed sludge is passed to the flash tank, which operates at atmospheric pressure. The sudden pressure drop leads to substantial cell destruction of the organic matter in the sewage sludge, which is then cooled to its optimum temperature before it is fed to the digesters.

Based on the proven ongoing success of Nigg’s biogas production, Scottish Water is considering the development of a further six sludge-to-energy facilities, which would represent a giant leap towards achieving the net zero target by 2040; five years earlier than the goal set by the Scottish Government.
Nigg’s Operation Team Lead, Ewan Dickie (left) with Landia's Paul Davies
Nigg’s Operation Team Lead, Ewan Dickie (left) with Landia's Paul Davies

One shouldn’t be blasé about hearing the word ‘innovation’ in the water industry, but some would argue that it has become so overused that it has begun to lose its real meaning due to static purchasing habits.

Nigg though is full of innovation, with constant, gradual progress, according to Simon Wrigglesworth, Operations Director for Scottish Water Grampian.

“We’re all for genuine innovation”, he said, “but sometimes it’s not just about new technology; it can be about doing something differently. Cambi’s THP has been around for over 20 years, and the chopper pump, which is a key part of the digester mixing system, was invented by Landia back in 1950”. 

‘Performance potential of the Landia digester mixing system is massive’

Landia’s digester mixing system pipes
Landia’s digester mixing system at Nigg now produces a consistent 400 – 420 cubic metres of biogas output per tonne of dry solids.

He added: “It’s fair to say that at first, investing in the Landia mixing system seemed a bold move, because others were seen as a much ‘cheaper’ capital cost.

But in an industry that promotes TOTEX, Landia were unmatched in providing meaningful numbers for the total cost of ownership, which showed that in the long term, they were in fact the least expensive option.

We believe in what Henry Ford once said, “If you do what you always do, you’ll always get what you’ve always had. For us, ‘average’, and “same old, same old,” won’t do.  “

We are adding resilience. The performance potential of the Landia digester mixing system is massive”.

Part of Nigg’s genuine innovation has also been its willingness to undertake a 3-month trial to co-digest residues from local distilleries and breweries with its domestic sewage. Not only were 58 tonnes of carbon saved, but the plant saw methane levels increase from 60% to 64%.

This first for the industry in the UK, which was led by the publicly owned water company’s commercial subsidiary, Scottish Water Horizons, could be just the start of a move that could have a major positive impact on a more circular and sustainable economy.

Keeping an ever-keen eye on all the production figures at Nigg is Process Engineer, Relina Dusa. During the past two years, she has worked on optimising the mixing with different run times, from 45 minutes per hour, down to 15.  Operation now rests at 28 minutes per hour; not half an hour or thereabouts, but a very specific 28 minutes.

‘Need for proper mixing’

Nigg WwTW Digester Tanks which have a high biogas yield
At energy-efficient Nigg WwTW, only 7 watts per cubic metre are needed for anaerobic digester mixing.

“We had a need for proper mixing and now we have it”, said Relina.  “It is important that we have experimented with different run times – and now I’m very happy with the biogas yield of between 400 and 420 (cubes of gas per tonne of dry solids) that we’ve now reached”.

“Over the past two years, I have worked closely with Tony Challinor at Landia. We never have to wait for answers and feedback. There haven’t been any issues with the mixing system – and though it might sound like a small point, the Landia service engineers always clean up properly after themselves and leave everything tidy. We work well together”.

From what has been learned and continues to be learned at Nigg, the prospect of Scottish Water developing six additional similar sites will be a landmark for the water industry in what can be achieved with sludge when optimising biogas production.

Simon Wrigglesworth added: “We’ve come a long way with Nigg already. The water industry rightly has to focus on achieving regulatory compliance, but we’re always looking at how we can maximise the generation of green energy, in order to meet our commitment to reducing and ultimately eliminating carbon”.

www.landia.co.uk

PR Ends

Tags: , ,
Previous Post
Biogas Farm Colouring Book Cover
General

Biogas Farm and Moo Poo Power Colouring Books

Next Post
Image text: "Is Natural Gas Renewable? 8 Reasons Why it's Not".
Biogas General

Is Natural Gas Renewable? 8 Reasons Why it’s Not in a Million Years

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Advertisement Banner for Home Biogas Buddy.
A note to our visitors:

By continuing to use this site, you are agreeing to our updated privacy policy.

Privacy Policy

0 Shares
Tweet
Share
Pin
Share